Woodhaven and Mill Creek Bridges
CLIENT/LOCATION
Regional District Central Okanagan (RDCO) – Kelowna, BC
DATE
2018/2019
Background
Cabin designed and constructed two vehicle bridges on behalf of the RDCO. The 23m Woodhaven bridge construction included site grading, installing Rip Rap, concrete abutments, a steel superstructure, and the timber decking and rails for the bridge. For the 14m Mill Creek bridge construction, Cabin administered the environmental monitoring throughout construction. The projects were completed on time and on budget. Cabin worked seamlessly with multiple contractors within a tight timeline.
Challenge
Stabilizing abutments of flood damaged channel along Bellevue Creek and installing large span vehicle bridge within the fish window.
Solution
Installing prefabricated ballast walls and concrete lock block abutments as well as placing rip rap in front of abutments for further support.
Vernon Office
Unit 20A - 100 Kalamalka Lake Rd.
Vernon, BC, V1T 9G1
778-475-3655
Nelson Office
Room #500A - 901 Front St.
Nelson, BC, V1L 4C1
778-463-1045
Kelowna Office
#2-3304 Appaloosa Rd.
Kelowna, BC, V1V 2W5
Nakusp Office
119 Broadway St W
Nakusp, BC V0G 1R0
250-265-3603