Woodhaven and Mill Creek Bridges

Woodhaven and Mill Creek Bridges

CLIENT/LOCATION

Regional District Central Okanagan (RDCO) – Kelowna, BC

DATE

2018/2019

Background

Cabin designed and constructed two vehicle bridges on behalf of the RDCO. The 23m Woodhaven bridge construction included site grading, installing Rip Rap, concrete abutments, a steel superstructure, and the timber decking and rails for the bridge. For the 14m Mill Creek bridge construction, Cabin administered the environmental monitoring throughout construction. The projects were completed on time and on budget. Cabin worked seamlessly with multiple contractors within a tight timeline.

Challenge

Stabilizing abutments of flood damaged channel along Bellevue Creek and installing large span vehicle bridge within the fish window.

Solution

Installing prefabricated ballast walls and concrete lock block abutments as well as placing rip rap in front of abutments for further support.

 

Woodhaven and Mill Creek
Woodhaven and Mill Creek
Cabin logo plain

Vernon Office

Unit 20A - 100 Kalamalka Lake Rd.
Vernon, BC, V1T 9G1
778-475-3655

Nelson Office

Room #500A - 901 Front St.
Nelson, BC, V1L 4C1
778-463-1045

Kelowna Office

#2-3304 Appaloosa Rd.
Kelowna, BC, V1V 2W5

Nakusp Office

119 Broadway St W
Nakusp, BC V0G 1R0
250-265-3603

General Inquiries

hello@cabinworks.ca

Looking for a new career?

©2025 Cabin Resource Management. All rights reserved.